Sign Installation Roadmap for Newbridge

Milestones

Description

Timeline

Site Survey 1. Structure of the Awning
Assess the structure to ensure it can support the signs.

ETA: 7 Days

 

Started: March 25

Completed: March 25

 

Status: Done

Installation Strategy 2. Installation Plan
Plan the placement and secure installation methods for both the channel letter signs and the LED sign.

ETA: 7 Days

 

Started: March 29

Completed: Apr 6

 

Status: Done

3. Size and Specification
Confirm the height and width of the signs atop the awning.

ETA: 7 Days

 

Started: Apr 5

Completed: May 2

 

Status: Done

Curved Signage Engineering Plans
Conceptualize how the LED sign will fit across the curved surface.

ETA: 15 Days

 

Completed: May 12

Status: Done

Channel Letters 4. Design Channel Letters
Initial designs for 8-inch tall channel letter signs.

ETA: 20 Days

 

Started: May 2

Completed: May 22

 

Status: Done

5. Channel Letters Revision
Create revision sets for 10-inch tall channel letter signs as per customer request.

ETA: 2 Days

 

Started: May 23

Completed: May 27

 

Status: Done

5. Color Revision
Create revision sets to match the brand colors.

ETA: 2 Days

 

Completed: June 11

 

Status: Done

Stamped Drawings 6. Stamp the Engineering Drawings
Update the drawings and strategies to meet engineering requirements and obtain necessary stamps.

ETA: 15 Days

 

Started: June 6

Completed: June 18

 

Status: Done

Permit 7. Pre-Permit Paperwork
Compile all required documents and details for the permit application.

ETA: 3 Days

 

Started: June 11

Completed: June 14

 

Status: Done

8. Permit Submission
Submit the permit application to the appropriate authorities for approval.

ETA: 1 Day

 

Started: June 18

Completed: June 18

 

Status: Done

9. Approval and Review
Revise drawings to meet local zoning ordinances.

ETA: 30 Days

 

Status: Pending

Production & Manufacturing 10. Manufacturing:
Start, sign assembly, frame fabrication, and channel letter customization.

ETA: 42 Days

 

Status: Open

Delivery 10. Shipping
Deliver the signs to the nearest assembly location.

ETA: 7 Days

 

Status: Open

Software Training 11. Software Session
Basics on programming the sign and ads.

ETA: 1 Hour

 

Status: Open

On Site Installation 12. Prepare
Connect the Signs to the Circuit.

ETA: 3 Days

 

Status: Open

13. Install
Securely mount the signs on the designated areas.

ETA: 3 Days

 

Status: Open

14. Test
Test the sign's color, electricity, network and connection.

ETA: 3 Days

 

Status: Open

Svg Vector Icons : http://www.onlinewebfonts.com/icon
We Value Your Privacy We use cookies to improve your experience, deliver personalized content, serve relevant ads, and analyze our traffic. By selecting "Accept All," you agree to the use of all cookies." For more information, see our Cookie Policy
You have successfully subscribed!
This email has been registered